Education building

Peter Symonds College

Download this case study

peter symonds college’s

rescue project for a new school facility

Modulek rescued a project that had run out of time for a traditional build solution. With our unique hybrid construction method, our design team were able to replicate the same three storey design, deliver and construct all within the timeframes required by the client.

peter symonds college

science block extension

key details

project overview

duration

10 weeks

Floor Area

400m2

services provided

Delivery

Design

Groundwork

Installation

Internal fit out and finishing

Management

Off site construction

Service Connections

requirements

With a completion date set for the start of the Autumn Term, the building was put into off-site production and delivered to site on the first day of the Summer Holiday.

The build was completed in just six weeks and was ready for students at the start of the Autumn Term as required.

the building

The new facility was designed to blend with the existing buildings on site, while also bringing into the setting a sleek modern external appearance.

Four Science Laboratories, a Library, and a Preparation Room gave the College the additional space they needed to enhance the learning and working environment for students and staff.

Part of the unique design of this building, was the three-storey construction.
The roof was designed in five sections; formed to the full pitch. A key to the project being completed on time as the internal work was able to progress the day after delivery.