Shinfield Parish Council

Shinfield Parish Council needed to demolish a tired and dated building and replace with a modern and fresh building at Spencers Wood Recreation Ground. The new community building was badly needed to replace an old and unfit for purpose building which was home to the parish preschool and also a vital community space that is available to hire. With a very tight building window, the whole project had to complete before the start of the September term.
Group 4 Copy

Project overview

Floor area:
300 m2
Project Completed:
12 weeks

Services provided

  • Design
  • Demolition
  • Groundwork
  • Service Connections
  • Manufacturing
  • Delivery
  • Installation
Group 4 Copy

A turnkey service was provided by Modulek to ensure that the demolition and build was as fast and efficient as possible and easier for the Parish Council to administrate.

Demolition, ground preparation, tree work and services were all part of the turnkey solution. The same site team were there for the delivery and swiftly got to work on the install and finishing.

Despite COVID restrictions in place through the summer months, the build remained on schedule and was completed in time for the start of the new autumn term.

The Pavilion has provided the Parish with an attractive and inclusive space which is available to hire for meetings and functions as well as provide the preschool with bright new modern facilities to offer their pupils the best learning environment.

Planning a public sector building?

View our brochure