project overview

duration

32 weeks

services provided

Delivery

Design

Groundwork

Installation

Internal fit out and finishing

Management

requirements

As part of our project management service for this client, a thorough ground investigation was carried out with site investigation specialists – sub surface

This was to examine and determine the stability of the site.

the building

The brand-new two storey bespoke building was designed to provide the very best learning environment for pupils and staff. From the early design stage every consideration was given to the areas that were needed so that the outcome would be exactly fit for purpose.

The new building is a truly state-of-the-art modern building, that was delivered within budget and on time and is a building that will last for many generations.