upton junior school’s
full turnkey package
The school required a full turnkey package for this project including demolition of the old site, full planning and design, off-site construction and installation. Modulek worked with construction consultants after a successful CIF bid was awarded for the building work.
key details
project overview
duration
16 weeks
completed
20220207
services provided
Demolition
Design
Foundations
Management
Paths and Fencing
Planning
Service Connections
Considerations for the wider community, such as neighbours. Logistics of how the materials are going to come into a busy school environment. All of these were considered by Modulek
sarah hickman – central liaison officer
viking academy trust
planning a new sports facility?
requirements
Involved from beginning to end, a turnkey service provided ease of communication and speed to this school project.
Access and aesthetics were key challenges for this build, as the school is located on a narrow residential road. Neighbours are also in close proximity, so getting the design of the Sports hall right was paramount to a successful planning submission.
the building
The school needed a brand new Sports hall with toilets, changing rooms and a kitchen area delivered within a fixed budget and timeframe set by CIF funding for the project. A true hybrid construction method was the only build method that could meet this requirement. A mix of modular for the changing and kitchen building was adjoined to a portal frame sports hall, using a traditional construction method assembled on-site.
The end result has provided huge benefits to children and sports leaders at the school. The self-contained facilities now allow children to change and access the toilets on site. This means little time is wasted through transitions back and forth from the schools main site and the sports hall. Allowing for more sport to be enjoyed and carried out.
The great thing about early engagement on a school project is all the early considerations that are made.
The great thing about early engagement on a school project is all the early considerations that are made.
Such as the discussions about safeguarding the children within the school environment. Considerations for the wider community, such as neighbours. Logistics of how the materials are going to come into a busy school environment. All of these were considered by Modulek, enabling the build to run as smoothly as possible.”
sarah hickman – central liaison officer
viking academy trust
flexible solutions for any size of sports and leisure facilities
With modular construction there is less time spent on site compared to traditional building methods, making your build faster and cost-efficient. Allowing you to create something that will benefit you and your community.
Modular buildings are flexible. They can be smart. They can be casual. They can be whatever you need them to be.